How is % Complete calculated?
Manual vs checklist-driven progress.
How Do I...?Project Manager · Team Member Last updated 13 Aug 2026
How % Complete works
- No checklist: you set % Complete manually using the slider.
- With a checklist: % Complete = (completed items ÷ total items) × 100. The slider is disabled.
Remove all checklist items to switch back to manual % Complete.